Fraud Warning: It has come to our attention that various international organizations or individuals have been offering false employment opportunities at Aecon Group Inc. These individuals will offer to fast track Canadian working visa applications in exchange for a payment. Such offers are fraudulent and intended to steal from the victims.

Aecon Group Inc. employment policies and processes in Canada involve personal interviews, and candidates who seek employment with us are never required to pay us any sum of money. To do so would be contrary to our business conduct guidelines and ethical practices. We take this matter extremely seriously and are working with the appropriate legal authorities to shut down such fraudulent schemes. Read more here
X
Safety First

Edmonton LRT – Edmonton, AB

This $26 Million contract for a Light Rapid Transit (LRT) tunnel under 111th Street represented Aecon’s first major contract with the City of Edmonton and formed part of the city’s larger $675 Milllion LRT expansion plan.

Scope of work involved two distinct deliverables:

  • 500m open-cut underpass
  • 90m tunnel to carry 111th Street over the tracks

Construction of the project began in January, 2006. As the excavation neared completion two years later in January, 2008, Aecon turned its attention to the concrete tunnel, a substantial structure with thicknesses measuring in at 600mm for the walls, 600mm for slab on grade, and 450mm for the roof. The schedule called for the slab to be poured first, after which the walls and the roof were completed with a single pour. The project was successfully completed and delivered in May, 2009.

Tunnel Dimensions:

  • 500m length, 12.5m width, 8m height

Quantities:

  • Concrete – more than 6,000 cubic metres
  • Excavation – more than 80,000 cubic metres